Jump to content

K-IV water project

From Wikipedia, the free encyclopedia

The K-IV water project (Urdu: کے فور پانی کے منصوبہ), abbreviated as K-IV, is a pending water supply project[1] being jointly developed by the provincial and federal governments in Karachi, Pakistan, to augment the city's daily water supply. The estimated cost was approximately Rs25.5 billion, which now increased to 150 billion PKR, while the project is designed to provide 650 million gallons of water daily to Karachi in three phases. The new water supply will be extracted from Keenjhar Lake through three water canals.[2][3][4][5][6][7] The project was slated for completion in mid-2019.[8] The K-IV water project is part of Karachi Bulk Water Supply Project.[9]

The responsibility of implementation of K4 project was handed over to WAPDA by the federal government in October 2020. The WAPDA vowed to complete the project in minimum time of two years so that the citizens of Karachi can benefit from it.[10] Like many other projects for Karachi, this project was once again delayed, till October 2023.[11]

Background

[edit]

The project was first conceived in 2002, and the project’s feasibility studies and design were completed by Osmani & Company Limited (OCL). Estimates prepared by the consultants in 2007–08 based on the preliminary designs were reviewed by different tiers of provincial and federal governments and finally the project was approved for Rs25.5 billion by ECNEC in the year 2011. Due to the negligence of federal and provincial governments during the span of decades, project costs have been increased from the original Rs25.5 billion to Rs150 billion and project work is still pending.[12]

Design

[edit]

The total length of the Phase 1 of the project is 120km, of which approximately 92km is canal, 10 km are siphons, and approximately 8 km are RCC conduits. There are 2 pump stations capable of pumping of 260 million gallons per day each, and three filtration plants: one of 130 MGD and two of 65 MGD capacity.

Construction

[edit]

Construction is being carried out by the Frontier Works Organisation conglomerate.[13][14][15][16] In November 2020, after taking responsibility to execute the project, WAPDA stopped working on the K-IV project by mentioning serious technical and design issues.[17]

See also

[edit]

References

[edit]
  1. ^ "What has happened with Karachi's K-IV water project? | SAMAA". Samaa TV. Retrieved 2021-06-01.
  2. ^ "Work begins on Rs25.6bn K-IV water project". DAWN. Retrieved 10 June 2016.
  3. ^ "Sindh CM inaugurates K-4 drinking water project after 9-year delay". The Express Tribune. June 10, 2015. Retrieved 10 June 2016.
  4. ^ "K4 Project - A $270 million project to double the capacity of Karachi's water supply system". slmdc.com.pk. Global Water Intelligence. Retrieved 10 June 2016.
  5. ^ "QAIM DIRECTS TO UNDERTAKE K-4 WATER PROJECT AT EARLIEST". Radio Pakistan. Retrieved 10 June 2016.
  6. ^ "First phase of water project 'K-4' to kick off in Karachi". Dunya News. Retrieved 10 June 2016.
  7. ^ "Rs650m fraud detected in Karachi's Bhambore project". Pakistan Today.
  8. ^ Bhagwandas (2018-03-06). "K-IV water project will not be operational this year, says minister". DAWN.COM. Retrieved 2018-03-06.
  9. ^ Azfar-ul-Ashfaque (2018-02-05). "Kamal warns K-4 project will not end Karachi's water woes". DAWN.COM. Retrieved 2020-10-14.
  10. ^ "Responsibility For Implementation Of K4 Project Has Been Handed Over To WAPDA". News. 2020-10-22. Retrieved 2021-03-30.
  11. ^ "Major water supply project for Karachi delayed". www.thenews.com.pk. Retrieved 2021-06-01.
  12. ^ "Karachi's K-4 project cost keeps rising, under development since 13 years". ARY NEWS. 2019-09-08. Retrieved 2021-06-01.
  13. ^ "Sindh govt ready to award K-IV project contract to FWO". Dawn (newspaper). Retrieved 14 June 2016.
  14. ^ "Sindh to hand over K-IV project to FWO". The Express Tribune. Retrieved 14 June 2016.
  15. ^ "Sindh govt decided to give K-IV project to FWO, to be launched on March 23". The Frontier Post. Retrieved 14 June 2016.
  16. ^ "Sindh to hand over K-IV project to FWO". News Pakistan. Retrieved 14 June 2016.
  17. ^ "WAPDA halts K-IV project citing serious technical issues". www.thenews.com.pk. Retrieved 2021-06-04.